I did the same, only front section is 12 inches. I know it’s over kill but heavy equipment work at the time I figured it was a good idea.I would use epoxy coater #4 steel rebar, and fibermesh concrete. I would use a 6 inch thick pour. Jim
no glass did one floor with it never again if your in cold part of country you will find out fast why all kind of pops from water going in and freezing little pop outs all overSteel or Fiberglas rebar for shop floor? What have you used?
You will never know you are rolling over a saw cut with a creeper. Tool cuts are a different animal.Still cuts are tough to roll a creeper on.
What is the correct location in a 6” slab?I used #4 rebar (1/2 inch) every 2 feet each direction, and tied at every intersection, and placed on chairs to make sure it was in the correct location in the concrete. Six inch floor thickness, and 1 foot in the entry door. Do not use rebar if less than 6 inches thick. The floor was saw cut and no other cracks, in place for 19 years.
I'd suspect because it's difficult to get good placement in the slab, especially if you're using 1/2" bar (1"where they cross). If I remember correctly, it should be between1/2 way and 2/3 up in the slab, with minimum 1-1/2" coverage. Our floor has 1/2" bar every 12", both directions, 6" thick and 8" thick within 18" of the edge all around.What is the correct location in a 6” slab?
Why shouldn’t I use rebar in a floor leads than 6”?
I would bet there are cracks in that floor, but they're only fine hairline and hard to see, probably because they're on a very solid base and/or not heavily loaded. Clean it well, hose it down and let it start to dry up, then you'll see them because they'll dry last. That is if it's bare concrete, not painted. It's concrete's nature, that's one of the reasons why it needs reinforcing.My floor is 6 inches for loaded semis at the time along with 8 inches on the apron in front. Thought it might need more with wet and frost as well as more loads of varying sizes. Has been there now almost 30 years. Cutting concrete is a joke it still cracks where it wants to. I would never cut a floor again for that. My floor was not cut nor cracked but the apron has cracked right corner ways of the cuts I didn't really want in it. It could be moisture since it is outside or it could be just being outside with frost. Still cuts are tough to roll a creeper on.
I can’t recite ACI or ASTM, but the standard was 1-1/2” to 2” clearance from earth in footings and foundations. Slabs typically saw the rebar placed in the bottom third.I'd suspect because it's difficult to get good placement in the slab, especially if you're using 1/2" bar (1"where they cross). If I remember correctly, it should be between1/2 way and 2/3 up in the slab, with minimum 1-1/2" coverage. Our floor has 1/2" bar every 12", both directions, 6" thick and 8" thick within 18" of the edge all around.
The more I think about it, I think the minimum coverage of steel is X times the thickness of the rebar at the very least, but I'm sure there are other factors that engineers would consider. I remember that most any of the jobs we worked on it was always at least 2" from the bottom and 2" from the top if not centred, especially if there was more than one layer of steel. I definitely agree about the importance of the underlying base integrity.I can’t recite ACI or ASTM, but the standard was 1-1/2” to 2” clearance from earth in footings and foundations. Slabs typically saw the rebar placed in the bottom third.
We just poured an 8” shop floor for a government job and the engineer wanted the reinforcement (#5, 16” OC EW) 2” from the TOS.
We’ve seen a trend to center and upper half placement of rebar. I don’t know who is teaching this. The integrity of a SOG has as much to do with soils and base under the slab as it does with reinforcing.
Let’s also understand that this new eco friendly green ground limestone powder and all the happy juice additives they are putting in concrete today is promoting shaling and cracking more than the portland concrete grandpa and uncle Tony poured in 1922 and even more than what we poured in 2023.
I use a concrete finisher. He likes wire and 6 inch thick floors. No cracking,Steel or Fiberglas rebar for shop floor? What have you used?
I’ve seen a lot of concrete demoed and don’t necessarily agree with “any”. Seen plenty of mesh, bar, and embeds that are still in good shape. Granted there are plenty of instances where it is not in good shape. If it is incased and sealed it should be ok.Whatever you do, use expoxy coated rebar or coated wire mesh. Why? any metal sealed in concrete will rust away. Also, would use the fiber mesh concrete if the cost is in line? Plus, I would put in a floor drain.
We sell tractor parts! We have the parts you need to repair your tractor - the right parts. Our low prices and years of research make us your best choice when you need parts. Shop Online Today.
Copyright © 1997-2025 Yesterday's Tractor Co.
All Rights Reserved. Reproduction of any part of this website, including design and content, without written permission is strictly prohibited. Trade Marks and Trade Names contained and used in this Website are those of others, and are used in this Website in a descriptive sense to refer to the products of others. Use of this Web site constitutes acceptance of our User Agreement and Privacy Policy TRADEMARK DISCLAIMER: Tradenames and Trademarks referred to within Yesterday's Tractor Co. products and within the Yesterday's Tractor Co. websites are the property of their respective trademark holders. None of these trademark holders are affiliated with Yesterday's Tractor Co., our products, or our website nor are we sponsored by them. John Deere and its logos are the registered trademarks of the John Deere Corporation. Agco, Agco Allis, White, Massey Ferguson and their logos are the registered trademarks of AGCO Corporation. Case, Case-IH, Farmall, International Harvester, New Holland and their logos are registered trademarks of CNH Global N.V.
Yesterday's Tractors - Antique Tractor Headquarters
Website Accessibility Policy